Lompoc's College Park Skate Park Waited Years for a Groundbreaking, and the Wait Shows Up in the Budget

College Park closed on Monday, October 19, and the city says it stays closed until the work is done. The park off West College Avenue, next to Lompoc High School, is closed to the public for the whole project. Construction is also affecting parking at the Lompoc Aquatic Center next door.

What's coming is a concrete skate park of 16,552 square feet, designed by Spohn Ranch Skateparks. It replaces the 10,000-square-foot park that opened in 2000. That's about 65 percent more skating surface. The plan's public input dates back four years, to when the city first asked skaters what they wanted. The time between that conversation and last month's groundbreaking added hundreds of thousands of dollars to the $5.15 million price tag.

The Plan the Public Weighed In On

The grant behind this project came first. In December 2021, the state awarded Lompoc $3,648,248 from the Proposition 68 Statewide Park Program to improve College Park. Design work with the public started the next year. The city's College Park Community Input Meeting, a Parks & Recreation Commission session on September 13, 2022 at City Hall, brought in consultants and city staff to gather community input on the skate park features. The Lompoc Record reported that an online survey followed, asking the public to weigh in on two proposed design concepts, with that feedback to be considered as the city developed a final design. A community meeting was announced for January 2023.

The scope that came out of that process covers much more than skating. The state's project page and the Lompoc Record's construction coverage list these pieces:

  • A new concrete skate park with lighting
  • Two half basketball courts, also lit
  • A playground with rubber surfacing, plus a lit game area
  • A picnic area under a shade structure
  • A prefabricated restroom building
  • A mural wall that the grant description says "will block wind"
  • Landscaping and fencing across the park, with accessible parking, seating, walkways and a drinking fountain

The mural wall is its own line item. The council approved a separate $118,068 purchase order with Great Western Recreation for it. It fits a town whose own city profile names its downtown mural program among the things Lompoc is known for. This wall also has a practical job, which the grant description spells out as blocking wind.

What the Wait Added to the Bill

The project's total budget is $5,152,966.97. That covers a $3.57 million construction contract with JJ Fisher Construction Inc. of Nipomo, plus design work, early procurement costs and supplemental appropriations. The contract award was Item 13 on the City Council's July 7, 2026 agenda, along with the staff report, bid tabulation and the mural-wall materials. The council approved it 4-1.

Here's how the money stacks up:

Piece of the budget Amount
Proposition 68 state grant, awarded December 2021 $3,648,248
Funding shortfall caused by rising construction prices roughly $1.5 million
Quimby Act fees the city is putting toward the gap $520,000
Park improvement impact fees the city is putting toward the gap $468,884.77
Added cost the city's community development director attributed to delays $600,000 to $700,000

Delay was a cost driver in its own right. The Lompoc Record reported that at the July meeting, City Manager Dean Albro said the city's procurement process had taken too long. Community Development Director Mario Guerrero Jr. confirmed the delays had likely added between $600,000 and $700,000. Guerrero also told the council that canceling would still leave the city owing about $1.2 million for design, equipment and professional services, none of it reimbursable, and he urged them to keep going.

The amenity list the grant described has held steady. The cost has climbed, and the delay accounts for a substantial share of that increase. The grant amount stayed the same. The city made up the difference from park funds it already held.

The Clock the Grant Sets

The Lompoc Record called the closure the start of "a year of construction." Under the grant terms, the city has to finish the work and file final documentation by December 2027. That December 2027 date is the state's deadline. On the Parks for All Californians page, the project is listed as "In Progress."

Read the dates together and the project's history is clear:

  1. 2000: The original 10,000-square-foot skate park opens at College Park.
  2. December 2021: The state awards the Prop 68 grant.
  3. September 2022: A community input meeting on skate park features, followed by a survey on two design concepts.
  4. July 2026: The council awards the construction contract, 4-1.
  5. October 19, 2026: College Park closes and construction starts.
  6. December 2027: The grant deadline to finish the work and file final documentation.

The Rest of the Block Keeps Its Hours

The closure covers the park itself. The two big facilities on the same property still have published schedules. Closing the green space doesn't shut down the whole College Avenue campus.

The Lompoc Aquatic Center has posted Fall 2026 hours and a Fall 2026 program guide. Programs include swim lessons, group exercise, lap swim and warm-water leisure swim. KSBY's October 20 report on the closure described parking impacts at the pool. It did not report that the pool was closing. The city's Fall 2026 facility hours are:

Day Aquatic Center hours, Fall 2026
Monday 6:00 a.m. to 1:00 p.m., 3:00 p.m. to 8:00 p.m.
Tuesday and Thursday 9:30 a.m. to 1:00 p.m., 3:00 p.m. to 8:00 p.m.
Wednesday 6:00 a.m. to 1:00 p.m., 3:00 p.m. to 8:00 p.m.
Friday 6:00 a.m. to 1:00 p.m.
Saturday 8:30 a.m. to 3:00 p.m.
Sunday 11:00 a.m. to 3:00 p.m.

Weekend recreation swim runs 1:00 p.m. to 3:00 p.m. on both Saturday and Sunday. The city asks visitors to allow extra time for parking and to follow posted construction signs.

The Lompoc Family YMCA at 201 West College Avenue lists facility hours of 9:00 a.m. to 8:00 p.m. on weekdays and 9:00 a.m. to 2:00 p.m. on Saturdays. It's closed Sundays. Its Teen Activity Program runs Monday through Friday from 2 p.m. to 7 p.m. Lompoc Unified middle and high school students can join for free, and registration is open for 2026-27 school-year childcare. Teens who used to spend after-school hours at the skate park have a free place to go on the same street.

Where to Ride Until College Park Reopens

Lompoc skaters will need to drive for now. The two closest options with recent news behind them are in opposite directions.

East, in Solvang: The Hans Christian Andersen Park skate park is at 633 Chalk Hill Road. Solvang lists it as opening at 10 a.m., with closing times that vary month to month. The park closes when it rains and has to dry out before it reopens. The park is in regular use. Solvang held a skate festival there on September 26, 2026.

North, in Guadalupe: KEYT reported that the skate park at Guadalupe's new Las Mujeres Park officially opened to the public on September 8, 2026. At that point the park wasn't entirely finished, and some fencing was expected to stay up for a couple of months.

Guadalupe's park is the newer of the two, opening six weeks before College Park closed.

Ground With a Long Résumé

College Park has been rebuilt before, and on a much bigger scale. The site was Lompoc's original airport and held a Navy blimp base during World War II. The city started leasing the land from Santa Barbara County in 1977 and opened it as a park in 1980. In 1999 the county donated the property to the city for the skateboard facility project. The Aquatic Center joined the park with its grand opening on October 21, 2006.

That makes the skate park the reason the city owns this ground at all. When College Park reopens, the facility that brought the land into city hands will be replaced by one about 65 percent larger, designed after the public input the city gathered in 2022.

Dianna Zlaket follows projects like the College Park rebuild because they shape daily life on the streets around them. If you own a home near West College Avenue and want to know how your property stands while the park comes back, request a free home valuation and Dianna will walk you through it.

Let’s Find Your Dream Home

Get assistance in determining the current property value, crafting a competitive offer, writing and negotiating a contract, and much more. Contact me today.
Follow Me on Instagram